01/06/2021

June 2021 Construction Update

High-level construction update:

  • McMullen Rd remains closed for upgrade works, with bulk earthworks and sewer installation now completed. Drainage installation is now underway.
  • Stage 1 internal sewer and drainage have been installed, with roads now boxed out and the water installation well underway.
  • We expect the kerb and channel installation to occur over the coming month and electrical installation to begin shortly.

Titles Update

  • Stage 1 titles are forecast in Q1 2022.

Stage 2:

High-level construction update:

  • Stage construction has commenced, with early preparation and bulk earthworks now underway.