September 2021
September 2021 Construction Update -
2021-11-10
Stage 1
- McMullen Rd remains closed for upgrade works, with road boxing underway.
- Stage 1 roads are now boxed out with curbs in and lots having been topsoiled in August.
- Electrical and NBN have been installed with light poles now installed.
Titles Update
- Stage 1 titles are forecast in Q1 2022.
Stage 2:
- Stage 2 bulk earthworks are well underway on site.
- Sewer installation works are nearing completion, with drainage works now underway.