Stage 4 - 2023-11-01

October 2023: 

Practical Completion has been achieved. The project team are working with authorities on achieving Statement of Compliance, which has been slightly delayed. Titles are now forecast for November 2023.

September 2023:

Asphalt works will be completed shortly and the authorities that are responsible for your services have completed their testing, and this will then lead to Practical Completion being issued. Titles are forecast in October 2023.

August 2023: 

  • Concrete works to be completed imminently. With topsoil works to follow.
  • Authority testing is underway.
  • Titles forecast: September – October 2023.

July 2023: 

  • Due to continuous wet weather days on site, the ability to complete base course asphalt works was impacted. However the recent sunny weather has allowed for these works to go ahead and base course asphalt has now been completed.
  • Concrete works underway.
  • Titles forecast: August-October 2023.

June 2023:

  • Kerb works complete.
  • Asphalt works underway.
  • Titles forecast: August-September 2023.

May 2023:

  • Kerb works underway.
  • Titles forecast: August-September 2023.

April 2023:

  • Watermain works complete.
  • Kerb works are to commence shortly.
  • Titles forecast: August-September 2023.

March 2023:

  • Watermain works are almost complete.
  • Class 3 and kerb works are to commence shortly.
  • Titles forecast for July-September 2023.

February 2023:

  • Drainage and stabilisation works continue.
  • Titles forecast for July-September 2023.

January 2023:

Our contractors have recently returned to site after the Christmas and New Year break. As work has only recently resumed on-site, there are no new updates from the Construction Update in December 2022.

December 2022: 

  • Sewer works have now commenced. These works will continue into January.
  • Stage 4 titles are forecast to be issued from July – September 2023

November 2022:

  • Civil works have now commenced and dam remediation works are now complete.
  • Stage 4 titles are forecast to be issued from July – September 2023

October 2022: 

  • Stage 3 bulk earthworks and dam remediation are ongoing.
  • Stage 4 titles are forecast to be issued from April – June 2023

September 2022: 

  • Bulk earthworks and dam remediation are currently underway.
  • Stage 4 titles are forecast to be issued from April – June 2023

August 2022: 

  • Bulk earthworks and dam remediation are under currently underway.
  • Stage 4 titles are now forecast to be issued in Q2 2023

July 2022:

  • Bulk earthworks and dam remediation are currently underway.