Stage 5
Stage 5 -
2025-03-25
We’re excited to share with you that construction on Stage 5 at Officer Fields has commenced.
We look forward to providing you with monthly progress updates on the construction of Stage 5.
Stage 5 Titles forecast for Q1 2026.
November 2025:
- All construction works have been completed.
- PC expected December 2025
September 2025:
- McMullen road upgrade works complete and open to the public.
- Wearing course being laid on the roads.
- Footpath and concrete works complete.
- Line marking and topsoiling underway.
August 2025:
- Kerb works are complete.
- Footpaths and asphalt works are underway.
July 2025:
- Kerb and concrete works underway.
- McMullen Road upgrade works are continuing with the roundabout currently under construction.
June 2025:
- Drainage works are complete.
- Kerb works are underway.
May 2025:
- Sewer works are complete.
- Drainage works are ongoing.
- Works along McMullen Rd are ongoing.
April 2025:
- Sewer and drainage works have commenced and are ongoing.
- Road upgrade works along McMullen Rd have commenced.
March 2025:
- Bulk earthworks currently underway with sewer works planned to follow.