Officer Fields Construction Update | October 2026
Spring has arrived at Officer Fields. Here’s the latest update on what’s happening across the community.
Stages 5 & 6 Landscape Works
Lots of houses are under construction across Stages 5 and 6. The pocket park and streetscape landscape works are now complete.
Stage 7
Civil works in Stage 7 are well underway, with servicing for the stage around halfway complete.
- Drainage and sewer connections are complete.
- Water servicing is approximately 50% complete.
- Titles are expected in Q1 2027.
Stage 8
YourLand is in the final stages of achieving council approval and engaging a civil contractor. Works are on track to commence in November, with titles expected between May and June 2027.
Childcare Centre
Construction on the Aspire Officer Childcare Centre is underway, with opening scheduled for Q4 2027.
Located at 92 McMullen Road, the new centre will be a great addition for young families in the community and will feature:
- Purpose-built rooms and connected outdoor spaces
- Fresh, nutritious meals prepared by an in-house chef
- Experienced and fully qualified educators
- Additional in-centre activities including face painting, magicians, sports and Tiny Mini Beasts and Insects
Find out more on the Aspire website
If you have any questions about Officer Fields, please email us at hello@officerfields.com.au.