May 2023
May 2023 Update -
2023-06-16
Due to wet weather construction within Stage 3 has been slightly impacted, however as works continue to progress here is a breakdown of current activity:
Stage 3:
- Internal topsoil and concrete works are underway.
- Asphalt works are to be completed shortly along Brown Road.
- Waterway rockwork complete. Topsoiling to commence shortly.
- Titles forecast: June – July 2023.
Stage 4:
- Kerb works underway.
- Titles forecast: August-September 2023.
Stage 1 Reserve Park:
Construction complete. Awaiting formal Practical Completion from Council