November 2022 update
November 2022 Update -
2022-11-16
Stage 3:
Watermains and drainage works are ongoing and progressing well.
Title Update:
- Stage 3 titles are forecast to be issued from April – June 2023
Stage 4:
Civil works have now commenced and dam remediation works are now complete.
Title Update:
- Stage 4 titles are forecast to be issued from July – September 2023